| 1 |
Taking the scaffold erection project into account, the heights and positions of the lower adjustment pins are adjusted. |
| 2 |
The starter legs are mounted on the adjustment rods, the distances are set using horizontal links, and the system is leveled. |
| 3 |
In the bays where the ladder platforms are located, the platforms are mounted on the starting feet. |
| 4 |
According to the project, the first module in the first row, where cross-connections are used, is constructed using panels, horizontal connections, and cross-connections. |
| 5 |
The first row is set up. |
| 6 |
The upper-level platforms (note the staircase detail) are installed. |
| 7 |
According to the project, the first module of the second row, where cross-connections are used, is constructed using a panel, horizontal connections, and cross-connections. |
| 8 |
The installation of the second row is completed, and the heel supports are installed. |
| 9 |
According to the project, the scaffolding system is anchored to the facade. |
| 10 |
The installation proceeds in the same order as specified in the project. |