| 1 |
Taking the scaffold erection project into account, the heights and positions of the lower adjustment pins are adjusted. |
| 2 |
The first row of frames is mounted on the lower adjustment shafts. |
| 3 |
Cross-braces are installed on the first row of frames, and the installation of the first row is completed. |
| 4 |
Scaffold connectors are installed. |
| 5 |
The second row of frames is installed. |
| 6 |
The pin and coupler are mounted on the scaffold connector to join the first and second rows of frames. |
| 7 |
Cross-braces are installed on the second row of frames, and the installation of the second row is completed. |
| 8 |
The process is repeated until the desired height for the project is reached. |
| 9 |
The heights of the DYB adjustment shafts are adjusted in accordance with the scaffold erection plan. |
| 10 |
Taking the scaffolding installation project into account, the main load-bearing beams are assembled according to their dimensions and overlap allowances. |
| 11 |
The secondary supports are installed in accordance with the scaffolding installation plan. |
| 12 |
Installation is completed with the assembly of the plywood. |